25/01302/FUL
Bassetlaw District Council
Status
Awaiting decision
Infrastructure
Received
20 Nov 2025
New homes
0
Summary
Construct a 400kV substation with associated facilities.
Full proposal
Erection of a 400kV Air Insulated Switchgear (AIS) Substation with one 400/275kV Supergrid Transformer (SGT) and One 400/33kV SGT and Construction of 16 Bays, Gantries, Control and Amenities Building, Permanent Access Road, Diesel Generator, Parking, Drainage, Lighting and CCTV Landscaping and Biodiversity Enhancement and Security Fencing.
Documents
ANNEX B GROUNDSURE ORDNANCE SURVEY MAPS PART 1 OF 3
Supporting Information
Not yet archived
· Original link
ANNEX B GROUNDSURE ORDNANCE SURVEY MAPS PART 2 OF 3
Supporting Information
Not yet archived
· Original link
ANNEX B GROUNDSURE ORDNANCE SURVEY MAPS PART 3 OF 3
Supporting Information
Not yet archived
· Original link
CONSTRUCTION DUST ASSESSMENT AND METHODOLOGY
Supporting Information
Not yet archived
· Original link
GROUND CONDITIONS AND CONTAMINATED LAND DESK STUDY REPORT
Supporting Information
Not yet archived
· Original link
OUTLINE CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN
Supporting Information
Not yet archived
· Original link
Have your say
Your comment matters. Councils must consider every representation that raises material planning considerations.