← Back to Enfield
Status
Application in Progress
Community facility
Received
07 May 2025
New dwellings
0
What you can do
Take Action
Make your voice heard. Authorities need to hear from people who support new homes.
Summary
Redevelopment to create surf lake complex, clubhouse, leisure facilities, campsite alterations and public park.
Full Proposal
Redevelopment of existing golf course and construction of a surfing complex comprising: (1) Outdoor surf lake (Use Class F2); (2) two-storey clubhouse including terraces, with cafe, surf shop, health and well-being facilities, changing facilities, offices (Use Class E), surfing operations and solar panels; (3) external plant, machine and store rooms structures for surf generation (Sui Generis); (4) renewal and alteration of existing campsite and the provision of additional accommodation and ancillary buildings (Sui Generis) with communal space; (5) use of land for pop up temporary outdoor events, with associated temporary structures; (6) free standing shelter with viewing deck; (7) engineering works including mounding and bunds; (8) public park, view point structure, pavilion and external play areas; (9) Pop up seasonal structures; (10) leisure facilities involving a pump track, skate bowl, sports courts, skate routes and external play areas; and (11) associated soft and hard landscaping, boundaries, lighting, flood lighting, parking and access routes.
Documents
Air quality assessment
Air Quality Assessment
APPLICATION FORM
Application Form - Without Personal Data
ARBORICULTURAL IMPACT ASSESSMENT REPORT
Tree Survey
ARBORICULTURAL METHOD STATEMENT ADDENDUM
Supporting Information
ARCHAEOLOGICAL ASSESSMENT
Supporting Information
BASEMENT IMPACT ASSESSMENT PART 1
Supporting Information
BASEMENT IMPACT ASSESSMENT PART 10
Supporting Information
BASEMENT IMPACT ASSESSMENT PART 11
Supporting Information
BASEMENT IMPACT ASSESSMENT PART 12
Supporting Information
BASEMENT IMPACT ASSESSMENT PART 13
Supporting Information
BASEMENT IMPACT ASSESSMENT PART 14
Supporting Information
BASEMENT IMPACT ASSESSMENT PART 15
Supporting Information
BASEMENT IMPACT ASSESSMENT PART 16
Supporting Information
BASEMENT IMPACT ASSESSMENT PART 17
Supporting Information
BASEMENT IMPACT ASSESSMENT PART 18
Supporting Information
BASEMENT IMPACT ASSESSMENT PART 19
Supporting Information
BASEMENT IMPACT ASSESSMENT PART 2
Supporting Information
BASEMENT IMPACT ASSESSMENT PART 20
Supporting Information
BASEMENT IMPACT ASSESSMENT PART 21
Supporting Information
BASEMENT IMPACT ASSESSMENT PART 22
Supporting Information
BASEMENT IMPACT ASSESSMENT PART 23
Supporting Information
BASEMENT IMPACT ASSESSMENT PART 24
Supporting Information
BASEMENT IMPACT ASSESSMENT PART 25
Supporting Information
BASEMENT IMPACT ASSESSMENT PART 26
Supporting Information
BASEMENT IMPACT ASSESSMENT PART 3
Supporting Information
BASEMENT IMPACT ASSESSMENT PART 4
Supporting Information
BASEMENT IMPACT ASSESSMENT PART 5
Supporting Information
BASEMENT IMPACT ASSESSMENT PART 6
Supporting Information
BASEMENT IMPACT ASSESSMENT PART 7
Supporting Information
BASEMENT IMPACT ASSESSMENT PART 8
Supporting Information
BASEMENT IMPACT ASSESSMENT PART 9
Supporting Information
Be Green
Other Relevant Information
Be Lean
Other Relevant Information
BIODIVERSITY SURVEY AND REPORT
Biodiversity Survey & Report
BNG METRIC
Supporting Information
BREEAM PRE-ASSESSMENT SUMMARY
Supporting Information
BUILDING LOCATION PLAN- P02
Revised Drawing
Bus Construction SPA
Other Relevant Information
CAMPSITE BUILDING 01 - EXISTING PLANS AND ELEVATIONS-P03
Revised Drawing
CAMPSITE BUILDING 02 - EXISTING PLANS AND ELEVATIONS-P03
Revised Drawing
CAMPSITE BUILDING 03 - EXISTING PLANS AND ELEVATIONS-P03
Revised Drawing
CE Memo
Other Relevant Information
CIL CALCULATION
Community Infrastructure Levy ? Completed Form
CIL FORM 1
Community Infrastructure Levy ? Completed Form
Circular economy
Other Relevant Information
CIRCULAR ECONOMY REPORT
Supporting Information
CLUBHOUSE-FIRST FLOOR PLAN-P02
Drawing
CLUBHOUSE-GROUND FLOOR PLAN-P02
Drawing
CLUBHOUSE-PROPOSED ELEVATIONS-P02
Drawing
CLUBHOUSE-ROOF PLAN-P02
Drawing
CLUBHOUSE-SECTIONS SHEET 1-P02
Drawing
CLUBHOUSE-SECTIONS SHEET 3-P02
Drawing
CLUBHOUSE-SETCIONS SHEET 2-P03
Revised Drawing
CO2 reporting spreadsheet
Other Relevant Information
Committee Report
Committee Report
COMMUNITY IMPACT STATEMENT
Supporting Information
CONFIRMATION OF BUILDING HEIGHTS REDACTED
Email
CONSTRUCTION MANAGEMENT PLAN
Supporting Information
CONTAMINATED LAND ASSESSMENT APPENDIX 2 PART 1
Land Contamination Assessment
CONTAMINATED LAND ASSESSMENT APPENDIX 2 PART 2
Land Contamination Assessment
CONTAMINATED LAND ASSESSMENT APPENDIX 3-5
Land Contamination Assessment
CONTAMINATED LAND ASSESSMENT APPENDIX 6
Land Contamination Assessment
CONTAMINATED LAND ASSESSMENT APPENDIX 7-8
Land Contamination Assessment
CONTAMINATED LAND ASSESSMENT APPENDIX 9-12
Land Contamination Assessment
CONTAMINATED LAND ASSESSMENT FIGURES AND APPENDIX 1
Land Contamination Assessment
CONTAMINATED LAND ASSESSMENT REPORT
Land Contamination Assessment
DELIVERY AND SERVICING PLAN
Supporting Information
DESIGNING OUT CRIME STATEMENT
Supporting Information
Draft S106
Legal Agreement
Draft Section 106
Legal Agreement
DRAWING REGISTER P01
Revised Drawing
ECOLOGY SURVEY AND ASSESSMENT
Supporting Information
Energy Memo
Other Relevant Information
ENERGY STRATEGY
Energy Statement
ENERGY STRATEGY-APPENDIX A-BRUKL-BE GREEN
Energy Statement
ENERGY STRATEGY-APPENDIX A-BRUKL-BE LEAN
Energy Statement
EXTERNAL LIGHTING STRATEGY
Lighting Assessment
EXTERNAL LIGHTING STRATEGY-APPENDIX C
Lighting Assessment
EXTERNAL LIGHTING STRATEGY-APPENDIX D
Lighting Assessment
FIRE STATEMENT
Supporting Information
FIRST AID BUILDING-P02
Revised Drawing
Flood Risk Addendum
Flood Risk Assessment
FRA AND SUDS STRATEGY PART 1
Flood Risk Assessment
FRA AND SUDS STRATEGY PART 2
Flood Risk Assessment
FRA AND SUDS STRATEGY PART 3
Flood Risk Assessment
FRA AND SUDS STRATEGY PART 4
Flood Risk Assessment
FRA AND SUDS STRATEGY PART 5
Flood Risk Assessment
FRA AND SUDS STRATEGY PART 6
Flood Risk Assessment
FRA AND SUDS STRATEGY PART 7
Flood Risk Assessment
GENERAL MAINTENANCE BUILDING-P03
Revised Drawing
GLA Circular Economy spreadsheet
Correspondence
GLA Circular Economy Template
Supporting Information
GLA Whole Life Carbon Template
Supporting Information
GREEN PERFORMANCE PLAN
Supporting Information
HARDWORKS OUTLINE SPECIFICATION
Supporting Information
HARDWORKS PLAN 1 OF 6
Drawing
HARDWORKS PLAN 2 OF 6
Drawing
HARDWORKS PLAN 3 OF 6
Drawing
HARDWORKS PLAN 4 OF 6
Drawing
HARDWORKS PLAN 5 OF 6
Drawing
HARDWORKS PLAN 6 OF 6
Drawing
HEALTH IMPACT ASSESSMENT FORM
Supporting Information
Inclusive Design Statement
Other Relevant Information
LANDSCAPE GA 1 OF 6
Drawing
LANDSCAPE GA 2 OF 6
Drawing
LANDSCAPE GA 3 OF 6
Drawing
LANDSCAPE GA 4 OF 6
Drawing
LANDSCAPE GA 5 OF 6
Drawing
LANDSCAPE GA 6 OF 6
Drawing
LANDSCAPE MAINTENANCE BUILDING-P03
Revised Drawing
LANDSCAPE PAVILION EAST-P02
Drawing
LANDSCAPE PAVILION WEST-P02
Drawing
LANDSCAPE VISUAL IMPACT ASSESSMENT
Supporting Information
LANDSCAPE VISUAL IMPACT ASSESSMENT FIGURES 1-6
Supporting Information
LANDSCAPE VISUAL IMPACT ASSESSMENT FIGURES 12-15
Supporting Information
LANDSCAPE VISUAL IMPACT ASSESSMENT FIGURES 16-21
Supporting Information
LANDSCAPE VISUAL IMPACT ASSESSMENT FIGURES 22-28
Supporting Information
LANDSCAPE VISUAL IMPACT ASSESSMENT FIGURES 7-11
Supporting Information
MATERIAL STUDY-ESCAPE STAIR/LOUVERED FACADE INTERFACE P01
Drawing
MATERIAL STUDY-LAKESIDE ACCESS-CONTROL ROOM P01
Drawing
MATERIAL STUDY-LOG WALL ENTRANCE EXPERIENCE- P01
Drawing
MATERIAL STUDY-LOG WALL-LOUVERED INTERFACE- P01
Drawing
Noise impact assessment
Noise Impact Assessment
OPERATIONAL WASTE MANAGEMENT PLAN
Supporting Information
Part_l_2021_gla_carbon_emission_reporting_spreadsheet
Supporting Information
PARTIAL ELEVATION - ESCAPE STAIR_ LOUVERED FACADE INTERFACE-P01
Drawing
PARTIAL ELEVATION - LAKESIDE ACCESS_ CONTROL ROOM-P01
Drawing
PARTIAL ELEVATION - LOG WALL ENTRANCE EXPERIENCE-P01
Drawing
PARTIAL ELEVATION - LOG WALL_ LOUVERED INTERFACE-P01
Drawing
PLANNING STATEMENT
Planning Statement
PRESS NOTICE 04/06/2025
Press Notice
PROPOSED TREE PLAN
Drawing
Rebuttal to GLA 1.8.25
Correspondence
received 10.6.25
Environmental Statement
received 10.6.25
Transport Assessment
received 10.6.25
Environmental Statement
REFUSE STORE-P03
Revised Drawing
REVISED DESIGN AND ACCESS STATEMENT PART 1 MASTERPLAN
Design & Access Statement
REVISED DESIGN AND ACCESS STATEMENT PART 2 LANDSCAPE
Design & Access Statement
REVISED DESIGN AND ACCESS STATEMENT PART 3 ARCHITECTURE
Design & Access Statement
Revisions for Urban Design letter
Supplementary Information
S106 Heads of Terms (draft)
Legal Agreement
SECTION 01
Revised Drawing
SECTION 02
Revised Drawing
SECTION 03
Revised Drawing
SECTION 04
Revised Drawing
SECTION BOUNDARY TREATMENT 01
Drawing
SECTION BOUNDARY TREATMENT 02
Drawing
SECTION BOUNDARY TREATMENT 03
Drawing
SECTION COMMUNITY PARKLAND
Drawing
SECURITY AND BOUNDARY PLAN
Drawing
SEQUENTIAL TEST
Supporting Information
sHRA
Environmental Statement
SITE CONTEXT SECTIONS-P01
Drawing
SITE CONTEXT SECTIONS-P01
Drawing
SOFTWORKS PLAN 1 OF 6
Drawing
SOFTWORKS PLAN 2 OF 6
Drawing
SOFTWORKS PLAN 3 OF 6
Drawing
SOFTWORKS PLAN 4 OF 6
Drawing
SOFTWORKS PLAN 5 OF 6
Drawing
SOFTWORKS PLAN 5 OF 6
Drawing
SOFTWORKS PLANTING SCHEDULE
Supporting Information
Statement of community involvement
Statement of Community Involvement
SURFBOARD SHAPER AND REPAIR HUT-P03
Revised Drawing
SURFBOARD STORE-P03
Revised Drawing
SUSTAINABLE DESIGN AND CONSTRUCTION STATEMENT
Supporting Information
SUSTAINABLE PROCUREMENT PLAN
Supporting Information
The location plan
OS Extract
Transport Assessment Addendum
Transport Assessment
TRANSPORT ASSESSMENT PART 1
Transport Assessment
TRANSPORT ASSESSMENT PART 2
Transport Assessment
TRANSPORT ASSESSMENT PART 3
Transport Assessment
TRANSPORT ASSESSMENT PART 4
Transport Assessment
TRANSPORT ASSESSMENT PART 5
Transport Assessment
TRANSPORT ASSESSMENT PART 6
Transport Assessment
TRANSPORT ASSESSMENT PART 7
Transport Assessment
TRANSPORT ASSESSMENT PART 8
Transport Assessment
TRANSPORT ASSESSMENT PART 9
Transport Assessment
TRAVEL PLAN PART 1
Travel Plan
TRAVEL PLAN PART 2
Travel Plan
TRAVEL PLAN PART 3
Travel Plan
TRAVEL PLAN PART 4
Travel Plan
TREE CONSTRAINTS PLAN S1
Tree Survey
TREE CONSTRAINTS PLAN S2
Tree Survey
TREE CONSTRAINTS PLAN S3
Tree Survey
TREE CONSTRAINTS PLAN S4
Tree Survey
TREE CONSTRAINTS PLAN S5
Tree Survey
TREE CONSTRAINTS PLAN S6
Tree Survey
TREE CONSTRAINTS PLAN S7
Tree Survey
TREE CONSTRAINTS PLAN S8
Tree Survey
TREE PLANTING SCHEDULE
Supporting Information
TREE PROTECTION PLAN S1
Tree Survey
TREE PROTECTION PLAN S2
Tree Survey
TREE PROTECTION PLAN S3
Tree Survey
TREE PROTECTION PLAN S4
Tree Survey
TREE REMOVAL AND RETENTION PLAN
Drawing
TREES LEGAL POLICY CONSTRAINTS
Tree Survey
UTILITIES AND FOUL SEWERAGE CONNECTION STRATEGY
Supporting Information
VALIDATION TABLE
Supporting Information
WAVE GENERATION BUILDING-P02
Revised Drawing
WAVE GENERATION CONTEXT ELEVATION-P01
Drawing
Whole life carbon report
Other Relevant Information
WHOLE LIFE CARBON REPORT
Supporting Information
WLC memo
Other Relevant Information
WLC template
Other Relevant Information