A/25/099954/NLA
Wigan Council
Status
Registered
Renewable energy
Received
30 Oct 2025
New homes
0
Summary
Construction of a 50MW battery energy storage system facility
Full proposal
Construction and operation of a 50MW battery energy storage system (BESS) facility including the erection of battery container units, inverters, 132kV substation, 33kV customer switchgear, storage container and welfare container, water tank, new internal access roads, resurfaced compound, installation of perimeter fencing and access gate, associated works; and landscaping
Documents
Have your say
Your comment matters. Councils must consider every representation that raises material planning considerations.